​COMPLETE.  This morning we’ve upgraded the power feed within a core rack at the Sheffield Data Centre.  Following on from last weekend’s core switch reload, we identified a power feed that needed replacing, so over the last 3 days we’ve had a new 3-phase supply installed into “Rack 1”, and this morning moved core switches over to the new supply.

The supply is fed from the UPS’s installed earlier this year, and takes over from the ATS previously installed in the rack.

The maintenance was communicated out to customers in advance, and logged on our status page @ https://hahosting.info